False Ceilings and Lighting Troughs in Hong Kong Flats: Headroom, Materials, the Rules and the Wiring Above

A Hong Kong living room with a perimeter false ceiling, a warm concealed lighting trough along the edge and a few small downlights, the centre of the ceiling kept at full height

Few Hong Kong flats are renovated without a false ceiling going in somewhere. It hides the air-conditioning pipes and the electrical conduit, squares off a beam, carries the downlights and the curtain pelmet, and gives the room the soft band of light along the edge that most people now think of as a finished ceiling. It is also the part of a renovation that quietly takes headroom away, in buildings where there was not much to begin with, and the part that seals in whatever is above it: the slab, the wiring, the LED drivers and sometimes a sprinkler head. This guide covers the decisions in the order they come up. What a false ceiling can fix and what it cannot; how low it can sensibly go; whether to drop the whole ceiling, part of it or only the perimeter; which material suits which room; how a lighting trough is built so it can be repaired later; which rules apply, including the ones for old ceilings; who may do the wiring above it; where the access panels go; and what the quotation should say. The facts come from the Buildings Department, the Fire Services Department, the Electrical and Mechanical Services Department's 2025 Code of Practice, the Environmental Protection Department and the Housing Authority, with industry guidance labelled as such.

The short answers first

  • Do I need approval for a false ceiling? An interior false ceiling hung from the slab inside a flat does not involve the structure of the building, so on our reading of the Buildings Department's definition it is exempted works: no plan approval and no registered contractor are required, but the work must still comply with the building regulations, including fire safety. The electrical work above it is a separate matter and must be done by a registered electrical worker.
  • How low can it go? No rule governs a renovation ceiling height. The Buildings Department's health minimum for rooms used for habitation, applied when building plans are approved, is 2.5 m, and that is the only official benchmark. Industry guidance puts a false ceiling within 200 mm of the slab where there is no beam.
  • Which material? Gypsum board on a metal frame is the usual choice for living rooms and bedrooms; aluminium strip panels are the common choice for kitchens and bathrooms because they tolerate humidity and lift out for access. No regulation requires either.
  • What about an old flat? Ceiling tiles and sprayed acoustic plaster in buildings from before the mid-1980s may contain asbestos and cannot be identified by eye. Have suspect material checked by a registered asbestos consultant before anyone disturbs it, and have spalling concrete or loose plaster repaired before the new ceiling covers it.
  • Why do lighting troughs fail? Often the driver, not the LED strip. Put the driver where an access panel reaches it, run the strip on its own dimmable circuit and keep the Work Completion Certificate (Form WR1) for the wiring.
The rest of this guide goes through each in full.

What a false ceiling does, and what it cannot fix

A false ceiling is a second ceiling hung below the structural slab on a frame, finished to look like the ceiling itself. In a Hong Kong flat it earns its place by doing several jobs at once:
  • Hiding services. Air-conditioning refrigerant pipes and condensate drains, the electrical conduit for the lights and, in a ducted installation, the fan coil unit and its ducts all run in the gap.
  • Squaring off beams. Most flats have a beam or two crossing the living room. A drop along the beam, or a full ceiling at the beam's level, turns a lump into a line.
  • Carrying the lighting. Recessed downlights need a cavity; a lighting trough (the concealed strip along the edge that washes the wall or the ceiling with light) is built into the ceiling's shape.
  • Finishing the window wall. A curtain pelmet along the window hides the track and lets the curtain hang from the ceiling line.
It is worth being equally clear about what a false ceiling cannot do.
  • It cannot stop water from above. Seepage from the flat upstairs or from a roof continues behind the new ceiling, stains and softens the board and eventually shows. The leak has to be traced and repaired first; our water seepage guide covers how.
  • It cannot make a defective slab safe. The Buildings Department lists spalling concrete and loose plaster in ceilings among the common defects of old buildings, with water staining, bulging and falling patches as the symptoms, and puts the repair on the owner. Covering the slab does not stop pieces falling onto the boards.
  • It cannot add height. Every part that is dropped is lower than before. In the 1970s to 1990s blocks of the Mid-Levels, which already have lower ceilings, a ceiling cannot simply be dropped across the whole flat; air-conditioner positions, pipe runs, trough depths and cabinet heights all have to be worked out at the measuring stage.
On headroom, there is one official figure to keep in mind. When the Buildings Department approves building plans, the minimum height of a room for habitation, for health reasons, is 2.5 m. That rule governs new buildings and not renovation, so a homeowner's false ceiling needs no approval, but a design that leaves less than 2.5 m under the ceiling of a living room or bedroom is going below the level the department treats as the health minimum. Industry guidance published jointly by the Hong Kong Arbitration Society, the Hong Kong Institute of Building Inspectors and a renovation platform recommends that, where there is no beam, a false ceiling is installed within 200 mm of the slab, and that where there is a beam the height is agreed with the contractor. Both figures are useful on a site visit: measure the slab height, subtract the beam depth and the pipe runs, and see what is left.
A bare concrete ceiling slab in a Hong Kong flat under renovation, with a deep beam crossing the room, insulated air-conditioning pipes and grey electrical conduit clipped along the slab, before the false ceiling frame goes up
Everything the false ceiling will hide is fixed first: the beam line, the air-conditioning pipes and the conduit.

Full, partial or perimeter: the three layouts

Most ceiling designs are one of three layouts, or a combination of them. A full false ceiling drops the whole room to one level, usually the underside of the deepest beam or the depth the air-conditioning needs. It gives the cleanest result, hides everything and lets downlights go anywhere, and it loses the most height. It also needs the most access panels, because every driver, joint and valve above it is sealed in. A partial false ceiling drops only where there is something to hide: a band along the beam, a soffit over the kitchen run or the corridor, a box around the air-conditioner. The rest of the room keeps the slab height. It is the usual answer where headroom is tight, and the junction between dropped and undropped areas becomes a design line that should land somewhere deliberate, such as the edge of the dining area or the line of a wardrobe. A perimeter trough drops a band around the edge of the room and keeps the centre at the slab. The band hides the pipes that run along the walls and carries the concealed strip that washes the ceiling with light. The centre reads as higher than the perimeter, which is why this layout is often said to solve low headroom; what it actually does is move the lost height to the edges, where people do not stand, and leave the middle alone. Along the window wall the band usually widens into the curtain pelmet. Whichever layout, let the beams decide first. The approved building plans, which can be inspected through the Buildings Department's online system, show where the beams and structural elements are, and a beam cannot be cut or chased to make a ceiling line work. Then let the air-conditioning decide: a wall-mounted split unit needs a box or a band at its height, and a ceiling-concealed fan coil needs a full ceiling over its length plus an access panel at the unit. Only then does the lighting plan fit in.

Materials: gypsum board, plywood and aluminium strip

Three materials cover nearly every residential ceiling in Hong Kong. Gypsum board (plasterboard, 石膏板) screwed to a light-gauge steel or timber frame is the standard for living rooms, bedrooms and corridors. Joints are taped and skimmed, the surface is painted, and curves and steps are easy to form. It does not like water: a condensate leak or seepage from above stains it and, left long enough, softens it. Plywood (夾板) is used where the ceiling has to carry weight or take screws later, such as the backing for a curtain track, a heavy pendant or a projector bracket, and for some curved or boxed details. It is usually combined with gypsum board rather than used alone. Aluminium strip or panel ceilings (鋁片天花) are the common choice for kitchens and bathrooms. The panels clip to a frame, tolerate humidity, wipe clean and lift out, so the exhaust fan, the water heater's connections and the lighting above them stay reachable without an access panel. Suppliers sometimes write that wet rooms "must" use aluminium; no regulation says so. It is a sensible default, with the trade-off that the look is a grid of panels rather than a smooth plane, and that the cheaper panels dent. Two points apply to all three. Exempted works must still comply with the building regulations, including fire safety, so the material and the finish should be ones the contractor can stand behind in writing; and in a Home Ownership Scheme flat the Housing Authority's decoration terms prohibit any material containing asbestos.
Gypsum boards being screwed to a light-gauge steel ceiling frame in a Hong Kong flat, one bay still open to show the hangers and runners
Gypsum board on a steel frame for the dry rooms; the open bay shows how little depth the frame itself needs.

Lighting troughs and layered light

A lighting trough is a ledge or slot built into the false ceiling that hides an LED strip, so the room sees the light on the wall or the ceiling and not the source. Done well it is the softest light in the flat; done badly it shows a row of dots, a dark gap where two strips meet or a flicker when it dims. The difference is mostly in how the strip is powered and how it can be reached. LED strips run on low-voltage direct current, commonly 12 V or 24 V, through a driver (the transformer, 火牛) and cannot be connected directly to the 220 V mains. The driver fails more often than the strip, so it belongs where an access panel or a cabinet top reaches it, not sealed inside the trough. An aluminium channel under the strip carries heat away and keeps the output even. The strip should have its own dimmable circuit, and the dimmer and the driver have to be matched to each other. General design references suggest a trough about 20 cm deep with an opening of about 10 cm for an even wash; that figure comes from generic design articles and is not a Hong Kong standard, so treat it as a starting point and test it on site with the strip you intend to use. Layered light is the point of the exercise. The trough gives the ambient layer; a few downlights or a track give task light over the dining table, the kitchen run and the reading corner; a pendant or a floor lamp gives the accent. The usual mistake is to pepper the ceiling with downlights and skip the layers, which gives a bright flat room with glare on every screen. For how this plays out in a living room, see our living room design guide. On the lamps themselves: since 1 December 2024, LED lamps sold in Hong Kong carry a mandatory energy efficiency label with five grades, Grade 1 being the most efficient, and the Electrical and Mechanical Services Department's selection tool groups colour temperature as warm white (2700 to 3000 K), cool white (4000 K) and daylight (6400 to 6500 K). Pick one colour temperature for the trough and the downlights in the same room. Note that the label covers replaceable lamps, not integrated downlights or strips, and that under common industry terms consumables such as bulbs, tubes, spotlights and LED strips are not covered by the renovation contractor's warranty, which is one more reason to keep the driver and strip specifications after handover.
A lighting trough along a new gypsum board ceiling during renovation, the LED strip hidden in an aluminium channel behind the ledge lip and washing warm white light down the wall
The strip sits in an aluminium channel inside the trough; the driver that powers it belongs somewhere a hand can reach.

The rules: exempted works, HOS terms, asbestos and old ceilings

Buildings Department. Building works that do not involve the structure of the building are exempted works under the Buildings Ordinance: no prior approval of plans, no consent to commence and no prescribed registered contractor are needed, provided the works do not contravene the regulations, which set the standards for fire safety, structural safety and drainage. The department's own examples are painting, internal plastering, wallpaper and the removal of non-load-bearing partitions that need no fire rating. On our reading of that definition, a false ceiling hung from the slab inside a flat falls on the same side of the line, and no minor works item covers it. The line is crossed the moment the job touches structure: cutting or chasing a beam to fit a ceiling, or opening the slab, is not exempted. The department's penalties for building works carried out without approval where it is required reach a fine of HK$400,000 and two years' imprisonment, and works carried out in a way that causes or is likely to cause risk of injury or damage reach HK$1,000,000 and three years. Home Ownership Scheme flats. The Housing Authority's standard decoration terms require all works to comply with the Building (Minor Works) Regulation's control procedures, prohibit materials containing asbestos, and prohibit removing or altering the miniature circuit breakers and earth leakage protection installed in the flat. They also note that the fused connection units provided in the kitchen and bathroom are for exhaust fans, and that the structural concrete walls are densely reinforced and must not be chased for pipes or switches. Our HOS renovation guide covers the rest of the terms. Asbestos. The Environmental Protection Department's guidance is that buildings built before the mid-1980s may contain asbestos materials, and its examples include acoustic plaster sprayed on ceilings and walls, ceiling tiles and wall boards. You cannot tell by appearance or colour, so suspect material is treated as asbestos-containing unless a registered asbestos consultant proves otherwise. If it is asbestos, the owner or occupier must hire a registered asbestos contractor to remove it and must give the department written notice at least 28 days before the work starts; carrying out abatement work without that notification is an offence with a maximum fine of HK$200,000 and six months' imprisonment, and the waste is chemical waste that cannot go out with household rubbish. All forms of asbestos have been banned from import and use since April 2014, so the risk is in what is already there, not in new materials. Old ceilings. Before the new ceiling goes up, the slab above it should be in a state that can be sealed in for many years. The Buildings Department's maintenance guidance lists defective concrete, spalling and loose plaster in ceilings as common in old buildings, caused by ageing, persistent leakage, salty water in the original mix or overloading, and the department has reminded owners after ceiling spalling incidents that inspection and repair are their responsibility. Our old-flat renovation guide explains how spalling is repaired.

Sprinkler heads and detectors behind the ceiling

Some flats have sprinkler heads or smoke detectors in the ceiling. Whether yours does depends on the building and the fire code it was built to, so check the slab before the design is drawn rather than assuming either way. Where they exist, the Fire Services Department's position is clear: sprinkler heads must be installed evenly across the area they protect, decoration works that change the layout must keep the coverage adequate and have it checked by a registered fire service installation contractor, and the operation of a sprinkler head must not be obstructed by any decoration, false ceiling, structure or stored goods. Relocating a head without the contractor's certificate (form FSI/314A or 314B) submitted before the works is listed by the department as an irregularity. The department's wording comes from its guidance for licensed premises; the principle, that a head must be able to reach the room below it, is the same in a flat. In practice this means the ceiling is designed around the heads, with each head brought down through the new ceiling by a registered fire service installation contractor, never boxed in above it. Ask the same contractor about any smoke detector. The building's management office may have its own requirements for works that touch the fire installations; ask before the contractor quotes, because the registered contractor's visit is a line in the budget and a date in the programme.

Electrics above the ceiling

The gap above a false ceiling is where most of a flat's new wiring ends up, and it is the part nobody will see again. It is fixed electrical installation work, so it must be done by a registered electrical worker employed by a registered electrical contractor, who inspects and tests the circuits and issues a Work Completion Certificate (Form WR1) before they are energised. The owner keeps the WR1; it is not submitted to the Electrical and Mechanical Services Department, but it is the document that proves the work was done and tested by the right person. The department's Code of Practice for the Electricity (Wiring) Regulations, 2025 edition, has several provisions that bear directly on ceilings:
  • Cables above a ceiling must be positioned so they are not liable to be damaged by the ceiling or its fixings, and must either have an earthed metallic sheath or be enclosed in earthed steel conduit, or have equivalent mechanical protection against penetration by nails and screws. A strip of twin-and-earth lying loose on the boards does not meet this.
  • Separate circuits. The code recommends that fixed lighting is fed by two or more final circuits, and that lighting circuits are electrically separate from power circuits, so that a fault on one does not black out the whole flat.
  • Fixed equipment on a socket circuit, such as a driver or a fan fed from a 13 A socket circuit, should be protected locally by a fuse of not more than 13 A with a switch in a readily accessible position, or by a miniature circuit breaker of not more than 16 A. That is the fused connection unit, and "readily accessible" is another argument for the access panel.
  • Working inside the ceiling. The code has a dedicated procedure for work inside a false ceiling: a risk assessment before starting, identifying the live circuits at and near the work, eliminating the risk of touching live parts within 1.5 m, proper lighting, and a strict prohibition on entering or working on fragile false ceilings without proper means of access or working platforms.
  • Bathrooms. In a room with a bath or shower, every circuit supplying equipment with exposed conductive parts within 2.25 m of the floor is protected by a 30 mA residual current device, and switches must be out of reach of a person using the bath or shower unless they are insulating pull cords; the department advises putting the switches for the light, the exhaust fan and the water heater outside the bathroom.
Two points of industry practice to settle in the quotation. Under common Hong Kong terms, the false ceiling counts as the finished surface, so the lighting cables above it are run in exposed conduit and the slab above is not plastered, painted or tiled; running the conduit concealed in the slab or walls is priced as an extra. And each new switch position needs a new cable run; if you are also planning smart switches, our smart switch guide explains the neutral-wire question that has to be answered before the ceiling closes.
Grey steel conduit and a metal junction box fixed to a concrete slab above a false ceiling frame, cables protected along their whole run
Above the ceiling the cables run in conduit clipped to the slab, protected against the screws and nails of the ceiling itself.

Air-conditioning, pipes and access panels

The air-conditioning usually sets the depth of the ceiling, and it is also the most common reason a finished ceiling gets opened again. A split-type system runs an insulated refrigerant pair and a condensate drain from each indoor unit to the outdoor unit. The refrigerant pipes need unbroken insulation to stop condensation forming on them inside the ceiling; the condensate drain needs a continuous fall to its outlet, because a flat or back-sloping drain fills, overflows and shows as a stain on the gypsum board under the unit. A ceiling-concealed fan coil adds the unit itself, its filter and its drain pan to the list of things above the boards. Everything that can fail or needs cleaning should sit behind an access panel: the LED drivers, the fan coil's filter and drain pan, the refrigerant and drain joints, the junction boxes, and the back of the exhaust fan where it is not under a lift-out aluminium panel. Decide the panel positions on the drawing, not on site, and make them large enough for a hand and a torch. A panel flush with the board and painted with it is barely visible; a ceiling with no panels at all is a ceiling that will be cut open. Other pipes cross the gap too: in some flats the drainage from the flat above runs below the slab, and in many older blocks the gas or water pipes are surface-mounted along the ceiling line. Moving any of them is separate work for the trade that owns it, not part of the ceiling job, and all of them need to stay reachable.
A finished white false ceiling with a flush access panel hinged open, revealing an LED driver and insulated air-conditioning pipes in the cavity above
An access panel at every driver and every pipe joint: the parts that fail should never need the ceiling cut open.

Sequence and timing

A ceiling is built in a fixed order, and most ceiling defects trace to a step done out of turn.
  1. Survey and strip. Check the existing ceiling for asbestos-era materials before anyone disturbs it, then strip the old ceiling and any loose plaster. Repair spalling concrete and trace any seepage before going further.
  2. Set out. Mark the beams, the slab height at several points (slabs are rarely level), the air-conditioner positions and the sprinkler heads, then fix the ceiling levels and the trough lines on the drawing.
  3. Services first. Run the refrigerant pipes, the condensate drains and the electrical conduit, with the cables protected as the code requires and the driver positions agreed. Have the fire installation contractor extend any sprinkler head.
  4. Frame. Fix the hangers and the frame to the slab. This is the noisiest stage, because every hanger is an anchor drilled into concrete.
  5. Board and panels. Fix the boards, form the troughs and the pelmets, and cut the access panels and the downlight openings.
  6. Finish. Tape and skim the joints, prime and paint; fit the aluminium panels in the wet rooms.
  7. Fit and test. Install the strips, drivers, downlights and fans, then the registered electrical worker tests the circuits and issues the WR1. Switch everything on, dim everything, and look at the trough from the far side of the room.
On timing, the noise law applies to the drilling. Under the Noise Control Ordinance, powered mechanical equipment such as drills, breakers and cutters may not be used for construction work between 7 pm and 7 am, or at any time on a Sunday or general holiday, unless a Construction Noise Permit is in force, and the Environmental Protection Department says a permit will generally not be granted for renovation in a residential flat. In 2021 the person in charge and a worker using a handheld electric cutter in a flat on a holiday were fined. The building's own management rules often narrow the hours further; our guide to renovation hours by building type has the detail.

Defects at handover

Check the ceiling three ways: with the room lights on, with only the trough on, and in daylight with everything off. Each shows a different set of faults.
  • Cracks at board joints within the first weeks usually mean joints that were not taped, or a frame that moves. Hairline cracks at corners of boxed sections are common and are made good under the warranty; a crack that opens is a frame problem.
  • Uneven trough light: visible dots on the wall mean the strip is too close to the opening or the channel is missing; a dark gap means two strips were joined badly or a driver is underpowered for its length; flicker on dimming means the dimmer and driver are mismatched.
  • Light leaking through a gap between the pelmet and the wall, or through a badly cut downlight opening, shows only with the room dark.
  • Downlights off line with each other or with the furniture below. Sight along the row.
  • Stains near the air-conditioner within the first summer mean a condensate drain without fall or insulation that was not continuous.
  • No access to a driver or a fan coil. This is the fault to catch on the drawing, because it is the one the warranty does not fix.
At handover, take the WR1 for the new circuits, the specification of the drivers and strips, and the positions of the access panels marked on a plan. Our guide to handover and defects covers which faults are normal settlement and which are not.

What drives the price, and what the quotation should say

The price of a false ceiling moves with the area dropped, the number of levels and curves, the length of trough, the number of downlight openings and access panels, the material (gypsum board, plywood backing, aluminium panels), the lighting specified, and whether the conduit above is exposed or concealed. Two flats of the same size can differ widely on these alone, which is why a price per square foot heard from a neighbour tells you very little. A quotation that can be held to should state:
  • the layout, with a reflected ceiling plan showing levels, troughs, pelmets and access panel positions;
  • the material and frame for each room, by name;
  • the number of lighting points, the driver and strip specification, and whose supply they are;
  • whether the conduit above the ceiling is exposed or concealed, and whether the slab above is finished at all (under common industry terms it is not);
  • who the registered electrical contractor is, and that a WR1 will be issued for the new circuits;
  • the warranty period and what it excludes (consumables such as lamps and strips are commonly excluded);
  • the duration. In the Consumer Council's 2020 study of renovation quotations, only five of eleven quotations stated how long the work would take.
Our guide to reading a renovation quotation goes through the rest line by line.

How we handle it

We take on projects as design and build, with design, construction and defects handled by one team under one contract. For a ceiling, that means the ceiling levels, the air-conditioning routes, the lighting plan and the registered electrical contractor's wiring are set out together before the frame goes up, and the access panels are on the drawing rather than cut in afterwards. After completion, Artwill provides a 12-month workmanship warranty covering the work we carry out ourselves. If you are planning a renovation and the ceiling is part of it, the first consultation is free, at our Wan Chai studio. Bring the floor plan and a few photos of the ceiling as it is, with the beams and the air-conditioner positions, and we will tell you how much height there is to work with and where a trough makes sense. Read about our renovation service, or book on WhatsApp.
FAQ

Common questions

Do I need Buildings Department approval for a false ceiling in my flat?

On our reading of the Buildings Department's definition, no. An interior false ceiling hung from the slab does not involve the structure of the building, so it is exempted works: no plan approval and no registered contractor are required, though the work must still comply with the building regulations, including fire safety. Cutting or chasing a beam, or opening the slab, is not exempted. The wiring above the ceiling is separate and must be done by a registered electrical worker, who issues a Work Completion Certificate (Form WR1).

How low can a false ceiling go in Hong Kong?

No rule fixes a renovation ceiling height. The Buildings Department's health minimum for rooms used for habitation, applied when building plans are approved, is 2.5 m, and that is the only official benchmark. Industry guidance recommends installing a false ceiling within 200 mm of the slab where there is no beam, and agreeing the height with the contractor where there is one. In older blocks with lower ceilings, a partial or perimeter layout keeps the centre of the room at the slab.

Should a kitchen or bathroom ceiling be aluminium?

Aluminium strip or panel ceilings are the common choice for kitchens and bathrooms because they tolerate humidity, wipe clean and lift out for access to the fan, the heater connections and the lighting. No regulation requires them, and suppliers' claims that wet rooms must use aluminium are sales claims. Gypsum board can be used where the room is well ventilated and there is an access panel, but it stains and softens if there is a leak.

Why does my lighting trough flicker or go dark in one section?

Often the driver, not the LED strip. A dark section means a bad joint between strips or a driver underpowered for the length it feeds; flicker on dimming means the dimmer and the driver are not matched. Drivers fail before strips, so each driver should sit behind an access panel or on top of a cabinet, and the strip should have its own dimmable circuit. Keep the driver and strip specifications from the contractor, because consumables are commonly excluded from the renovation warranty.

My building is from the 1970s. Can I just strip the old ceiling tiles?

Not until they have been checked. The Environmental Protection Department's guidance is that buildings from before the mid-1980s may contain asbestos materials, including ceiling tiles and sprayed acoustic plaster, and that appearance tells you nothing; suspect material is treated as asbestos unless a registered asbestos consultant proves otherwise. If it is asbestos, a registered asbestos contractor must remove it, with written notice to the department at least 28 days before, and the waste is chemical waste. Starting abatement work without that notice carries a maximum fine of HK$200,000 and six months' imprisonment.

Ready to start your project?

Free first consultation, no pressure. We'll map a realistic scope and budget for your space.

WhatsApp us to book a free consultation

First consultation is free, by appointment at the Wan Chai studio.

12-month warranty Itemised quote, fixed at signing Weekly site reports 500+ projects since 2004
ADDRESS 19/F., 103 Hennessy Road, Wan Chai, Hong Kong
OPENING HOURS
Monday 10:00 AM to 7:00 PM
Tuesday 10:00 AM to 7:00 PM
Wednesday 10:00 AM to 7:00 PM
Thursday 10:00 AM to 7:00 PM
Friday 10:00 AM to 7:00 PM
Saturday Closed
Sunday Closed
INSTAGRAM FACEBOOK YOUTUBE 小紅書
Artwill WeChat QR code

Open WeChat, Discover, Scan

Or save the QR and import it from your gallery.